QScope

Instructions

No instruction, no variation

A variation with no instruction behind it is the first thing an auditor pulls out, and the first thing a payer refuses. The register exists so that the answer is on file before the question is asked.

  • Your own numbering, not an imposed sequence
  • Date issued and issued by, held against every entry
  • Register prints and exports to CSV

30 days free, no card.

Instructions
Instruction AI-019
TypeArchitect’s instruction
Date issued2 June 2026
Issued byFielding & Partners
Cost effectYes
Variation raisedNone

An instruction is the authority for a variation. This one has a cost effect and nothing has been raised against it.

Numbering that still makes sense in three years

Instructions are referred to by number in correspondence long after the project team has changed.

Keep the contract’s own numbering and the file stays readable; renumber it to suit a spreadsheet and it does not. QScope holds the number you give it, the date, who issued it and what it said, and prints the register as a document. Dayworks and variations both point back at it.

Instructions

The two gaps that cost money

The first is an instruction that changes the cost of the works and never becomes a variation.

  • Instructions with a cost effect and no variation raised, shown in red
  • Verbal instructions awaiting written confirmation, shown in amber
  • Architect’s instruction, CA instruction, employer’s instruction, CVI and site instruction
Instructions
Register
Instructions
24
Unconfirmed
2
No variation
3
AI-018 · Revised door scheduleVariation VO-11
AI-019 · Additional drainageNo variation raised
CVI-004 · Verbal, 12 MayAwaiting confirmation
With a cost effect19 of 24

AI-019 changes the cost of the works and has no variation against it. As things stand it will not reach the final account.

Variations

What the instruction authorises

An instruction is the authority.

  • Each instruction shows the variation raised against it
  • Basis of valuation and contract clause held on the variation
  • Instructions with a cost effect and no variation flagged in red
Variations
VO-11 Revised door schedule
InstructionAI-018
Basis of valuationContract rates
Contract clauseJCT 5.6.1
Extension of time1 day
Subtotal£2,150.00

Link the instruction to the variation and both point at each other, so the account can be traced from the authority to the figure and back.

See it running before you sign up

RFIs

The question before the instruction

An instruction often begins as a question.

  • Question, who it was raised with, and the date raised
  • Answer and the date it was given
  • Days outstanding counted from today, not from memory
RFIs
Outstanding on this project
QuestionRaisedStatus
Confirm lintel spec over new opening4 AugOpen 16 d
Drainage invert level at MH311 AugOpen 9 d
Finish to exposed soffit2 AugAnswered
Open on this project2

When a question becomes an instruction it becomes a variation, and the register keeps the thread from RFI to instruction to change on the same project.

Dayworks

Work carried out under instruction

Where work cannot be measured at contract rates it is valued as daywork, and every sheet needs the instruction that authorised it.

  • Separate additions for labour, materials and plant
  • Only agreed sheets carried to the final account
  • Sheets with no instruction linked are flagged
Dayworks
Sheet DW-014
Labour £2,000 + 130%£4,600
Materials £3,000 + 15%£3,450
Plant £500 + 20%£600
Sheet total£8,650

Each daywork sheet links back to the instruction in the register, so the authority for the labour, materials and plant is on file before the sheet is submitted.

Every other function on the Instructions screen

6 functions the sections above do not cover, each as it works in the program.

Functions 1 to 3

01Each instruction has a Notes field for anything that does not fit the other boxes.
02A client-side guest can read the register, and a guest with edit rights can add to it.
03A new instruction takes the architect named in the project settings as Issued by, and you can change it.

Functions 4 to 6

04Instructions marked Superseded or Withdrawn drop out of the warning, so the red count shows only live instructions.
05On an NEC contract the register is headed Project Manager's instructions.
06Instructions confirmed in writing is one of the measures on the project health card.

Who it is for

One change, four people it touches

You are applying

You price the change and defend it

You price the instruction, submit the variation and defend it when it comes back cut. Instructed work with no variation against it is money you have already spent.

Applying for payment
the same measurement

You are certifying

You value the change and answer for it

You value the variation from the other chair and account for what you cut. The register you keep is the one the final account will be argued from.

Certifying payment

You are doing both

You build the change, paid or not

You absorb the small changes as they come, and the ones nobody wrote down are the ones you end up building for free.

Doing both yourself

You are reporting

You fund the change, priced or blind

You check that scope changes are priced and approved before money moves, because an unpriced variation is risk the facility is carrying blind.

Recommending a drawdown

The client, the architect and the tenderer are not on this list. They are the people you let in on a link: they see the one document you sent them, answer it, and that answer is written into the record. No account, no licence, no charge, on every plan.

FAQs

The questions this page raises most often, answered without a sales pitch at the end.

A confirmation of verbal instruction. Where the contract administrator gives an instruction other than in writing, the contractor may confirm it in writing, and it takes effect if the administrator does not dissent within the period the contract allows.

Only the person named in the contract. An instruction from a clerk of works or a project manager who is not named does not vary the works, however reasonable it was.

No. It shows you the instruction has a cost effect and no variation against it, and you decide what to raise. Automatic creation would produce variations nobody had priced.

Yes, as CSV, and it prints as a formal register for issue with the final account.

From the blog

The part nobody teaches you, written down

Three pieces from the same corner of a contract as this page, answered at length and without a sales pitch at the end.

All 174 pieces

Keep reading

The three parts this page leans on

No instruction, no variation

A variation with no instruction behind it is the first thing an auditor pulls out, and the first thing a payer refuses. The register exists so that the answer is on file before the question is asked.

30 days free, no card.

Rather ask first? Write to help@qscope.co.uk and you will get a reply within one working day, Monday to Friday.