QScope

Defects

The schedule that releases the last of the retention

By the time the rectification period ends the team has moved on and the job is closed in everyone’s mind. A percentage of the contract sum is still sitting with the employer, and nothing prompts anybody.

  • Date notified, date to be made good by, date actually made good
  • Location and trade against every item
  • Outstanding, in progress, made good, disputed and accepted as is

30 days free, no card.

Defects
Schedule
On the schedule
23
Outstanding
4
Overdue
2
014 · Block B stair · JoineryMade good 8 Aug
015 · Plant room · M&EOutstanding
016 · Roof terrace · WaterproofingOverdue
Making goodBlocked

Four items remain outstanding, so making good cannot be certified. Certifying it now would release the final retention for work nobody has done.

Not a snagging list

Snagging at practical completion and the schedule of defects at the end of the rectification period are different documents with different consequences.

The second one is contractual: the certificate of making good depends on it, and the balance of the retention depends on that certificate. QScope keeps notified and made good as separate dates on every item, because those two dates are what show the period was operated properly if anyone examines it later.

Completion

The block is the feature

The certificate of making good releases the balance of the retention.

  • Warning on the certificate while items remain outstanding
  • Schedule prints as a formal document for issue to the contractor
  • CSV export for circulation to the trades
Completion
Certificate of making good
Rectification period ended7 Sep 2027
Items on the schedule23
Made good19
Retention to release£12,500

The remaining retention is released on this certificate. QScope will not let it be issued while the schedule still shows outstanding items.

Completion

The certificate that started the clock

The rectification period runs from practical completion, and the schedule has to be issued before that period ends.

  • Rectification end calculated from the completion certificate
  • Schedule due date driven by the same date, not entered twice
  • Half the retention already released at practical completion
Completion
Rectification clock
Practical completion7 Sep 2026
Rectification period12 months
Schedule issued22 Aug 2027
Rectification ends7 Sep 2027

The schedule is issued inside the rectification period, not after it. Issuing it late is a weaker position, not a stronger one.

See it running before you sign up

Retention

The money the schedule is protecting

The schedule of defects exists because a percentage of the contract sum is still held, and the certificate of making good is what releases it.

  • Balance of the retention held against the making good certificate
  • Figure on the dashboard matches the retention notice
  • Release date shown next to the amount
Retention
Held to end of rectification
Rate now
2.5%
Held
£12,500
Release
7 Sep 27
Retention released at practical completion£12,500.00
Balance held to rectification end£12,500.00
Released on making good£12,500.00

The balance is released on the certificate of making good, which QScope blocks while the schedule shows outstanding items.

Project record

Photographs that settle the disputed item

A defect argued two years after handover turns on evidence, and the evidence is the dated photograph nobody filed.

  • Photographs tied to the item and the date they were taken
  • Correspondence and defect notices filed against the job
  • The audit trail records who filed what and when
Project record
Evidence for the schedule
DocumentStatus
Defect 015, plant room, photographs6 files
Defect notice, issued 4 AugFiled
Making good correspondenceFiled
Site photographs, week 1418 files

QScope keeps the photographs, the correspondence and the notices against the same project as the schedule, so the file is assembled as you go rather than reconstructed the week before an adjudication.

Defects

The Defects Notification Period, under FIDIC

On a FIDIC contract the rectification period is the Defects Notification Period under Clause 11, and it runs from the Taking-Over Certificate rather than practical completion.

  • Rectification period maps to the Defects Notification Period, Clause 11
  • Certificate of making good maps to the Performance Certificate, 11.9
  • Period runs from the Taking-Over date, counted in calendar days
Defects
Defects Notification Period (FIDIC)
Taking-Over Certificate7 Sep 2026
Defects Notification Period12 months
Notified defects made good19 of 23
Performance CertificateBlocked

The Defects Notification Period runs from Taking-Over in calendar days. Four items remain, so the Performance Certificate cannot be issued and the second half of the retention stays held. The figures are a starting point to verify for the jurisdiction.

Who it is for

One programme, four clocks running on it

You are applying

You claim the time before damages run

You notice delay, name the relevant event and claim the time before the damages clock does the arguing for you.

Applying for payment
the same measurement

You are certifying

You award the weeks and stop the clock

You assess the extension from the other chair, and the completion certificate you issue halves retention and stops the damages clock.

Certifying payment

You are doing both

Your delay is your own money waiting

You run the programme and the money together, and a completion date that slips moves the whole payment tail with it.

Doing both yourself

You are reporting

A late job is a loan running long

You track completion against the facility term, because a job that finishes late is a loan that runs longer than the model.

Recommending a drawdown

The client, the architect and the tenderer are not on this list. They are the people you let in on a link: they see the one document you sent them, answer it, and that answer is written into the record. No account, no licence, no charge, on every plan.

FAQs

The questions this page raises most often, answered without a sales pitch at the end.

At the end of the rectification period, within the period the contract allows. Issuing it a year late is not a stronger position, it is a weaker one.

No. The certificate of making good states that the notified defects have been made good. Liability for defects that were not apparent continues for the limitation period.

Yes. Export to CSV, or print the schedule as a formal document with the trade against each item.

Record it as disputed rather than leaving it outstanding. It still blocks the certificate, which is correct, and the status makes clear that the block is a disagreement rather than a delay.

The rectification period is the Defects Notification Period under Clause 11, running from the Taking-Over Certificate, and the certificate of making good is the Performance Certificate under Sub-Clause 11.9. QScope blocks that certificate while items remain outstanding, exactly as under a UK form, and counts the period in calendar days.

From the blog

The part nobody teaches you, written down

Three pieces from the same corner of a contract as this page, answered at length and without a sales pitch at the end.

All 174 pieces

Keep reading

The three parts this page leans on

The schedule that releases the last of the retention

By the time the rectification period ends the team has moved on and the job is closed in everyone’s mind. A percentage of the contract sum is still sitting with the employer, and nothing prompts anybody.

30 days free, no card.

Rather ask first? Write to help@qscope.co.uk and you will get a reply within one working day, Monday to Friday.