Cost estimate
Descriptions and units come from the QScope library on the NRM1 tree. The quantities, the rates and the allowances are yours, and the estimate you price is the one the contract and the valuations are built from.
30 days free, no card.
Projects › Meridian House › Budget
Meridian House
Acting as Monitoring surveyor
Cost plan
Rate is the base price. Markup is added on top; Total includes the markup.
| Ref | Description | Qty | Unit | Rate £ | Total £ |
|---|---|---|---|---|---|
| Demolition and Strip Out | 14,224.00 | ||||
| 1.1 | Isolate electrics (Excluding 3 phase main works) | 1 | item | 1,400.00 | 1,400.00 |
| 1.2 | Isolate plumbing and heating | 1 | item | 1,400.00 | 1,400.00 |
| 1.3 | Removal of kitchens / utilities / sanitarywares | 1 | item | 2,240.00 | 2,240.00 |
| 1.4 | Demolition of external / internal walls | 1 | item | 3,080.00 | 3,080.00 |
| 1.5 | Removal of existing drainage | 1 | item | 1,344.00 | 1,344.00 |
| 1.6 | Soft strip of internal finishes | 1 | item | 2,520.00 | 2,520.00 |
| 1.7 | Site clearance | 1 | item | 2,240.00 | 2,240.00 |
| External Walls and Lintels | 616.00 | ||||
| 2.1 | External monocouche renders and beads | 5 | nr | 123.20 | 616.00 |
| Timber Carcassing and Studwork | 27,440.00 | ||||
The bar under the estimate shows the cost per square metre, the number of items and how many still have no rate, so a gap is visible before the total is quoted.
The QScope library
The QScope library holds 4,876 items on the NRM1 tree, in 13 sections, 58 groups and 358 families, written to NRM2 measurement.
1 · Section
2 · Group
Open it from any row with Ctrl and Space. The description and the unit are already right, so the bill reads the way a quantity surveyor expects.
Rate build-up
Any rate can be built up from four kinds of resource, and the net rate is applied back to the line.
The build-up is internal and never leaves your account. Once applied, the rate is locked on the line with a built up tag, and the net rate excludes overheads and profit.
Allowances
Design development, risk and inflation are set as percentages and shown separately, never buried in the rates.
No allowance is filled in for you. A percentage left blank says not set, so a cost plan with no risk allowance says so on the page.
Cost plan by link
Save a version and send it by link: the link always shows a saved version, never the live estimate.
Cost, markup and rate build-ups never leave your account for anyone. A withdrawn link says it has been withdrawn by the sender.
Into the contract
An estimate in a different file from the valuations is two versions of the truth, so here it is the same record.
A new valuation is built from the cost plan and carries each line's percentage on from the last one, so nothing is retyped between the estimate and the certificate.
Cost estimate
Overheads and profit can be added as one percentage of the subtotal and shown on every total.
On screen: “Cost plan settings”, “OHP · overheads & profit”, “No additional OHP”, “Add OHP · % of subtotal”.
Cost estimate
Build up quantity, the Σ beside Qty, measures a line from lengths, widths, heights and numbers, with deductions.
On screen: “Build up quantity”, “Measurement unit”, “Length m”, “Width m”.
Cost estimate
Print builds the cost plan document, called Bill of Quantities on contractor projects.
On screen: “Print”, “Cost plan”, “Bill of Quantities”, “Section subtotal · x% of the cost plan”.
27 functions the sections above do not cover, each as it works in the program.
Functions 1 to 14
Functions 15 to 27
Who it is for
You are applying
You value it, and the certificate cuts itYou value the work line by line and submit the application. When the certificate lands short, the difference is argued line by line too, and your valuation is the evidence.
Applying for paymentYou are certifying
You cut it, and you sign your nameYou value the same lines from the other chair and issue the certificate. Every percentage you cut has to survive the question of why, a month or a year later.
Certifying paymentYou are doing both
You value your own work, aloneYou price it, you value it and you apply for it yourself, between site visits. The certificate still has to add up as if a surveyor had built it.
Doing both yourselfYou are reporting
You certify value the lender pays onYou certify value in place so the lender can release the next tranche. The valuation is the same arithmetic; the reader was never on site.
Recommending a drawdownThe client, the architect and the tenderer are not on this list. They are the people you let in on a link: they see the one document you sent them, answer it, and that answer is written into the record. No account, no licence, no charge, on every plan.
The questions this page raises most often, answered without a sales pitch at the end.
No, and that is deliberate. The library carries descriptions and units on the NRM1 tree. The rate is yours, typed in or built up from labour, materials, plant and subcontract.
The 286 standard UK resources carry indicative prices from public UK sources. They are a starting point, not our rates, and your own project prices always take priority.
Their own package, priced at their own rates. No other rates, no margin and no build-ups.
Yes. Apply to All Certificates rebuilds the draft valuations from it. An issued valuation is never rewritten.
From the blog
Three pieces from the same corner of a contract as this page, answered at length and without a sales pitch at the end.

Since the domestic reverse charge, most VAT-registered construction supplies inside CIS swap who accounts for the tax: the customer does, not the supplier. Why the invoice looks wrong and is right, the end user exception, and the cash flow effect nobody warns you about.
Read now
The honest answer is that either beats a two-page quote, and the choice mostly follows who the client is: RIBA’s domestic forms are written for homeowners, JCT Minor Works for jobs run by a professional. And Minor Works is not a small version of the big forms.
Read now
For construction the tax point is usually the earlier of invoice or payment. Retention is different: its tax point waits until the retention is received or invoiced.
Read nowKeep reading
Build the estimate, set the allowances, print the order of cost estimate and send the client their cost plan by link.
30 days free, no card.
Rather ask first? Write to help@qscope.co.uk and you will get a reply within one working day, Monday to Friday.