QScope

Valuations and certificates

Interim valuations that add up every time

Value line by line, by percentage or by a fixed sum. Retention, previously certified and this period calculate as you type, and no line can be certified past 100 per cent.

  • Value line by line, by percentage or by a fixed sum, on the same screen
  • Both routes are capped, so the total to date cannot exceed the line
  • Your practice name and your logo on the document, never QScope branding

30 days free, no card.

Interim certificate PC-04 · 15 Aug 2026

This period, exc VAT£24,180.00
Less retention at 5%(£1,209.00)
Due this certificate, exc VAT£22,971.00

Forty two lines across seven sections, valued by percentage and by fixed sum on the same certificate. The net is the gross less the retention movement, and it is calculated, not typed in.

Everything through one percentage, and a fudge column at the bottom

The valuation is the easy part.

Some lines are a percentage of measured work. Some are a lump sum, a provisional sum drawn down in tranches, or dayworks off a sheet. A certificate is only a payment notice if it carries the dates the Construction Act attaches to it, and the pay-less deadline is the one that turns a valuation into a liability.

Two ways to value

Two ways to value, on the same certificate

Some lines are a percentage of measured work, some are a lump sum, a provisional sum drawn down in tranches, or dayworks off a sheet, and forcing everything through a percentage is how spreadsheets end up with a fudge column.

  • A fixed sum stays fixed when you correct the contract value of the line
  • Both routes are capped so the total to date cannot exceed the line
  • The printed certificate always shows a percentage, so the client sees a normal valuation

Client valuations · lines on PC-04

Frame to first floor55 per cent£6,820.00
Brickwork to first floor40 per cent£4,800.00
Scaffolding hirefixed sum£1,250.00
This period, exc VAT42 lines across 7 sections£24,180.00

Click the per cent on any line to switch it to a fixed sum. The rest of the certificate does not change, because underneath both routes produce the same figure.

The document

The certificate carries the statutory statement

Section 110A of the Construction Act requires a payment notice to state the sum considered due and the basis on which it is calculated.

  • Your firm logo and practice name, never QScope branding
  • Signature blocks that follow your role in the contract
  • Document named correctly for JCT, NEC or the Scheme

Payment certificate · what the document carries

LetterheadYour practice
Contract formJCT SBC/DB
Payment due15 Aug 2026
Sum considered due£22,971.00

The valuation schedule is the basis on which that sum is calculated, and the document says so on its face rather than leaving the client to work it out.

Counted on the certificate, not afterwards

The routes, the dates and the contract forms are what the program actually carries, and each one is read out of the code that runs the valuation rather than rounded up for a page like this.

2

ways to value a line, on the same certificate

4

statutory dates printed on the face of every certificate

7

contract forms carrying their own statutory periods

The two routes are a percentage of the line or a fixed sum for the period. The four dates are the date payment falls due, the last day for a payment notice, the last day for a pay-less notice and the final date for payment. FIDIC is one of the forms, and it counts its own sequence in calendar days.

Statutory dates

The dates that turn a valuation into a notice

A certificate is only a payment notice if it carries the dates the Construction Act attaches to it.

  • Due date, payment notice deadline, pay-less deadline and final date for payment
  • Weekends and England and Wales bank holidays excluded automatically
  • Printed on the face of the certificate, not just shown on screen

Final date for payment · one due date, four contract forms

JCT SBC/DB29 Aug 2026
JCT IC/MW29 Aug 2026
NEC3/4 ECC29 Aug 2026
Scheme02 Sep 2026

Same certificate, same due date of 15 Aug 2026. The pay-less deadline moves with it: 24 Aug 2026 under JCT, 22 Aug 2026 under NEC, 25 Aug 2026 under the Scheme. The valuation is the easy part; the pay-less deadline is the one that turns a valuation into a liability.

Retention

Retention comes off the certificate, once

The £1,209 deducted for retention on this certificate is not a setting buried in a menu.

  • Full rate during the works, half rate after practical completion
  • Deducted from the certificate, not applied on a separate note
  • Release date calculated from the rectification period

Retention · held after PC-04

Retention this certificate5 per cent£1,209.00
Held to date£4,205.75
Practical completion07 Sep 2026
Half rate from that datereleased in full on 07 Sep 20272.5 per cent

It is a deduction from the sum due, and it has to be the same figure the client sees on the retention notice, so the number here is the number on the notice.

See it running before you sign up

Variations

Approved variations arrive as valuation lines

Under JCT they are valued in the certificate, so retention runs down one track and nothing is paid twice.

  • Approved variations pull in as normal valuation lines
  • Retention deducted once, in the certificate, as JCT expects
  • A certified variation cannot also be marked paid, so nothing counts twice

Variations · approved for PC-04

VO-01 Additional window100 per cent£1,000.00
VO-03 Revised M&E layouthalf of £3,240.00£1,620.00
Variations this period£2,620.00

VO-01 and VO-03 are not paid on a separate note. The certified percentage is written back to the variation record, so the two never drift apart.

FIDIC

On FIDIC the Statement becomes a certificate

On a FIDIC contract the Contractor submits a monthly Statement, the Engineer values it and issues an Interim Payment Certificate, and the Employer pays.

  • Measured work valued under Clause 12, the same line by line valuation
  • Interim Payment Certificate within 28 days of the Statement, payment within 56, on the 1999 Red Book defaults
  • Retention released against Taking-Over and the Defects Notification Period, not practical completion

FIDIC Red Book 1999 · IPC-04

Statement received15 Aug 2026
Interim Payment Certificate by28 calendar days12 Sep 2026
Employer to pay by56 calendar days10 Oct 2026

There is no payment notice and no pay-less notice. The days are counted in calendar days and stay editable for the Particular Conditions of your contract; the published defaults are a starting point to verify, not legal advice.

Who it is for

Four chairs, one valuation on the table

You are applying

You value it, and the certificate cuts it

You value the work line by line and submit the application. When the certificate lands short, the difference is argued line by line too, and your valuation is the evidence.

Applying for payment
the same measurement

You are certifying

You cut it, and you sign your name

You value the same lines from the other chair and issue the certificate. Every percentage you cut has to survive the question of why, a month or a year later.

Certifying payment

You are doing both

You value your own work, alone

You price it, you value it and you apply for it yourself, between site visits. The certificate still has to add up as if a surveyor had built it.

Doing both yourself

You are reporting

You certify value the lender pays on

You certify value in place so the lender can release the next tranche. The valuation is the same arithmetic; the reader was never on site.

Recommending a drawdown

The client, the architect and the tenderer are not on this list. They are the people you let in on a link: they see the one document you sent them, answer it, and that answer is written into the record. No account, no licence, no charge, on every plan.

FAQs

The five that come up most often about certificates that have to stand up as payment notices.

Yes. You can enter the bill directly or bring it in, then every certificate values against those lines. Section subtotals and omissions carry through, so the certificate structure matches the bill the client already has.

You cannot. QScope caps each line at the contract value less what has already been certified, and tells you how much is left on that line rather than silently trimming the figure.

No. Documents carry your practice name and your logo. QScope does not appear on anything you send a client.

Yes, and each has their own login so the audit trail records who prepared each certificate. If two people open the same project, QScope warns the second one rather than letting one overwrite the other.

Yes. Set the contract form to FIDIC and the certificate becomes an Interim Payment Certificate valued from the Contractor’s Statement, with the 28 and 56 day sequence counted in calendar days on the 1999 Red Book defaults. The dates are published starting points to verify against your Particular Conditions and jurisdiction.

From the blog

The part nobody teaches you, written down

Three of the questions this page raises, answered at length and without a sales pitch at the end.

All 174 pieces

Keep reading

The three parts this page leans on

Put one valuation in and see the certificate come out

Your own lines, your own retention rate and your own contract form. The percentages, the fixed sums, the statutory dates and the statement come out of the same screen, and nothing is retyped between the valuation and the document you send.

30 days free, no card.

Rather ask first? Write to help@qscope.co.uk and you will get a reply within one working day, Monday to Friday.