Cash flow
Projects do not fail because they were unprofitable. They fail because the money went out before it came in, and nobody had modelled the gap.
30 days free, no card.
This is the cash flow of the contract. Your own labour, plant and overheads are not in it, because the program does not hold them, and pretending otherwise would be worse than saying so.
Late payment is common enough that a forecast built on contractual dates is optimistic by default.
QScope lets you model the behaviour you actually see, so the peak reflects the world rather than the contract. The tail matters as much as the peak. Retention and an unagreed final account keep the position negative long after practical completion, and a forecast that goes positive at handover is wrong by exactly that amount.
Cash flow
Every certificate already carries a valuation date, a due date and a final date for payment.
Remaining cycles are projected from the valuation schedule, with the uncertified balance spread on an S-curve, because that is how construction actually runs: slow, fast, slow. An even spread flatters the early months and hides the peak.
Client Valuations
The money coming in is not a guess.
The receipt in the forecast is the net figure after retention, on the date the money actually arrives, not the day the valuation was signed.
Statutory payment dates
A forecast that pays on the valuation date is weeks early and wrong in your favour.
The receipt for this certificate falls in the forecast on 29 Aug 2026, fourteen days after the due date, not on the valuation date two weeks earlier.
Cash flow
The gap between doing the work and being paid for it is what the peak measures, and that gap is set by the contract form and the jurisdiction.
The 56 day period runs from the Statement in calendar days, so the receipt sits nearly two months out. On a UK contract the same certificate would land a fortnight after the due date. The defaults are editable for the Particular Conditions, and the figures are a starting point to verify locally.
Reports
The peak funding requirement is only useful once it leaves the screen.
QScope prints the forecast alongside the reports a QS already sends, so the cash position sits next to the cost report and the payment schedule rather than in a spreadsheet nobody else can open.
Who it is for
You are applying
You report cost against money securedYou report cost against the sum you have actually secured, and the difference between the two is the conversation with your own board.
Applying for paymentYou are certifying
You report on figures you certifiedYou report to the client on a job you certify, and the report has to reconcile with the certificates you signed.
Certifying paymentYou are doing both
Your record is the only report there isYou are the report: what you have applied for, what has been certified and what is still to fund, pulled from your own record.
Doing both yourselfYou are reporting
You turn the record into a drawdownYou turn the project record into a drawdown recommendation, and the figures have to reconcile before the lender releases a pound.
Recommending a drawdownThe client, the architect and the tenderer are not on this list. They are the people you let in on a link: they see the one document you sent them, answer it, and that answer is written into the record. No account, no licence, no charge, on every plan.
The questions this page raises most often, answered without a sales pitch at the end.
No, and it does not claim to be. It is the cash flow of one contract: money in from client certificates against money out to subcontractors. Own labour, plant and overheads sit in your accounts, not here.
From the valuation schedule in project settings, with the uncertified balance spread across the remaining cycles. You choose an S-curve or an even spread.
Yes. Retention is withheld on the forecast certificates at the correct rate, and released on the dates the certificates and the rectification period produce.
It prints as a document. Whether it suits a funder depends on what they need, and most will want your own cost base alongside it.
Yes. It places receipts on the FIDIC payment period, 56 calendar days from the Statement on the 1999 default, and carries the currency for the market. The 28 and 56 day periods are editable for the Particular Conditions, and country figures are starting points to verify locally.
From the blog
Three pieces from the same corner of a contract as this page, answered at length and without a sales pitch at the end.
Walking away does not mean downing tools, that is breach, it means finishing what you owe and declining the next job. The arithmetic of a bad client’s true cost, the difference between a hard client and a harmful one, and how to leave without a war.
Read nowThe handshake is an inch away and the ask arrives: knock a bit off and we are done. It works because you have already spent the evenings and can smell the job. The three answers that keep your margin, and the one response that trains clients to repeat it.
Read nowAnyone who answers with a percentage is guessing about your business with your money. Markup is two numbers wearing one name: overhead recovery, which is arithmetic from your own accounts, and profit, which is a decision. How to work out yours.
Read nowKeep reading
Projects do not fail because they were unprofitable. They fail because the money went out before it came in, and nobody had modelled the gap.
30 days free, no card.
Rather ask first? Write to help@qscope.co.uk and you will get a reply within one working day, Monday to Friday.