QScope

QScope replaces the quantity surveyor where there isn’t one, and helps the one you have.

Cost estimates, tendering, variations, valuations and retention, through to the final account.

Works to

  • JCT
  • NEC3/4
  • RIBA
  • Scheme
  • FIDIC
Meridian House · T/2026
Cash still to come in
£193,298.68
contract sum less all received
Contract sum
£291,767.93
adjusted
Certified, exc VAT
£151,719.32
52.0% complete
Received, exc VAT
£98,469.25
VAL-01 paid plus deposit
Left to certify
£140,048.61
after two valuations
Retention held
£7,585.97
5% of certified to date
What needs you 2 items
VAL-02 awaiting payment issued 29/08/2026
£52,664.10
Deposit to recover comes back through valuations
£7,000.00
Neither has a statutory clock.
Statutory clock VAL-02
Payment due
02/09/2026
Notice by
07/09/2026
Pay less by
11/09/2026
Final date
16/09/2026
Valuations click a line to open it
VAL-02 Issued · 29/08/2026 · this valuation £55,435.90, retention movement £2,771.80
£52,664.10
VAL-01 Paid · 31/07/2026 · this valuation £96,283.42, retention movement £4,814.17
£91,469.25

30 days

No card to start, and nothing to cancel if you decide to walk away.

1,653

Distinct priced item descriptions, ready to pull before you write a line.

4 dates

Counted from your own contract, so you are not the one remembering them.

The same job, seen from three different sides

One record, three people who need different things from it.

Pick the one that sounds like your week. What sits underneath is the same project record, but what you are trying to get out of it is not, and each page behind these buttons is written for one reader.

You build it, and there is no QS on the job

Applications go out on the day they fall due, every variation carries the instruction that raised it, and the money still owed to you is a figure you read off one screen rather than one you rebuild by hand on a Sunday evening with three spreadsheets open in front of you and no way to check it.

The job is priced, valued and certified in the same place, so the application you send is built from the bill you already agreed.
  • Applications built straight from the bill you priced
  • Notice dates counted from the contract you confirmed
  • Variations carrying the instruction that raised them
  • Retention tracked with both release dates against it
  • A certificate you can send out on the same afternoon
A builder on a timber-framed extension, checking a phone on site

Three ways money leaves a job that nobody meant to lose

None of these is a story about software. They are what happens on a construction contract when the paperwork is late, missing, or impossible to rebuild. The figures are from the job in the panel at the top of this page.

£12,964.10

One missed date

The notice nobody served in time

The contractor applied for £68,400.00 and the certificate says £55,435.90. If neither a payment notice nor a pay-less notice is served by the deadline, the sum applied for becomes the notified sum and falls due in full.

QScope counts that deadline from the periods you confirm from your own contract, prints it on the face of the certificate and repeats it on the notice you send to the client.

£7,585.97

Sitting with somebody else

Retention with no date against it

That is the retention held on this job today. Half comes back at practical completion and half at the end of the defects period, twelve months on. Neither half comes back on its own, and nobody is counting the days.

The rate drops to half automatically once practical completion is certified, the release date is counted from it, and the notice you send shows the same figure as your dashboard.

12 months

Later, in a negotiation

The valuation you cannot rebuild

A year after issue, somebody asks how a figure was arrived at. From a spreadsheet you rebuild it from memory and hope it matches the paper you sent. Whoever cannot show their working concedes the point, right or wrong.

A QScope certificate freezes at the moment of issue, and every change made since then sits in a trail that nobody can edit, that carries a name and a date against it, and that exports to CSV.

Four dates, counted from your contract, not from ours

You confirm the payment periods once, from your own contract. Everything below is counted from them and printed on the certificate and on the notice. These are the dates from the job in the panel at the top of this page.

SECOND CHANCE 2 Sep Payment due 7 Sep Payment notice due s.110A(1) limit 11 Sep Pay-less notice due from the contract 16 Sep Final date for payment from the contract

Miss the payment notice on 7 September and the pay-less notice on 11 September, and the sum applied for becomes the notified sum. You pay £68,400 instead of the £55,436 you certified: £12,964 you never agreed to, on one job, for one missed date.

The five-day period for a payment notice is the limit set by s.110A(1) of the Housing Grants, Construction and Regeneration Act 1996. The fourteen days to the final date and the five days for a pay-less notice on this job come from the contract, not from statute, which is why QScope asks you to confirm them rather than assume them. Try it on your own contract.

One project, from the first estimate to the final account

The same record carries the job from the day you price it to the day the account is agreed. What you estimated is what the valuations measure against, what the valuations certified is what the final account adds up.

Nothing is retyped between one stage and the next, so a figure you entered in the first week is still the figure being argued from in the last one.

Try it free for 30 days Your own job and your own contract dates. No card, and nothing to cancel if you walk away.

Ten stages, one record

  • Cost estimate
  • Import
  • Tender comparison
  • Contract setup
  • Valuations
  • Variations
  • Approvals
  • Payment dates
  • Retention
  • Final account

Work that disappears, and paperwork that arrives

On the left, what a commercial team does by hand most months and stops doing. On the right, what one job set up this afternoon can already put in an envelope. Same change, seen from both ends.

Six things you stop doing

01Rebuilding the valuation sheetThe bill you priced is the bill you value against, every month to the final account. No new tab, no copied formulas, no cell that quietly stopped adding up in March.
02Working out the dates by handConfirm the payment periods once, from your contract. Due date, payment notice, pay-less deadline and final date are counted from them and printed on the paper.
03Chasing what retention is heldFull rate during the works, half after practical completion, released on the date. The notice you send and the figure on your dashboard cannot disagree.
04Assembling the cost report at month endCertified to date is the certificates added up. Anticipated final cost against the approved budget is already there when somebody asks for it on a Friday.
05Reformatting documents before sendingCertificates, notices and reports come out laid out by a practising QS, on your letterhead, ready to go as they are.
06Reconstructing a figure from memoryIssue freezes the rates and the contract context. The trail says who changed which figure and when, and it cannot be edited by anyone, including the account owner.

Six things you can already send

01An interim payment certificateRetention, previously certified and VAT worked out, with every payment date on it.
02A pay-less noticeCarrying the same sum as the certificate, with the deadline already counted.
03A retention noticeWhat is held, by certificate, with both release stages named.
04A cost reportAnticipated final cost against the approved budget, for the client or the funder.
05A variation order and registerInstruction, valuation rule and net effect on the contract sum.
06A guest link for the clientThey see their position and nothing of your cost report. Guests never count towards your plan.

Issue one valuation, in about a minute

Not a video and not a tour. Move three percentages, press issue, and read the certificate that comes out. The arithmetic and the dates are the ones the program uses, on the same job as the panel at the top of this page.

  1. 1Value the lines
  2. 2Issue it
  3. 3Read the certificate

Drag a percentage. Every figure below recalculates as you move it, and no line can go back below what was already certified.

Gross this period£0.00
Less retention movement£0.00
Due this period, exc VAT£0.00
VAT at 20%£0.00
Total due£0.00

Retention is held on the cumulative certified value, so the certificate shows the movement for this period, not three per cent of this valuation. That is how the program calculates it.

Built for the commercial side of the job

Every tool here is post-contract. Most construction software was built for drawings and snagging, then had a money tab added later. QScope starts where the money starts: the bill, the valuation and the certificate.

Interim valuations Value line by line, by percentage or by a fixed sum. Retention calculates as you type and no line passes 100 per cent. See how it works Cost estimate Descriptions and units from the SMM7 and NRM libraries. The quantity and the rate are yours, and so is the bill you price. See how it works Import a pricing document Read a spreadsheet or a PDF on your own machine, with the arithmetic rebuilt from the items rather than from the totals. See how it works Statutory dates Enter a due date and get the payment notice, the pay-less deadline and the final date under your own contract form. See how it works Variations Instruction, valuation rule, extension of time and loss and expense on one record, pulled straight into a certificate. See how it works Tender comparison Your document and up to eight returned bids, matched by item reference and not by row order, levelled as you choose. See how it works Retention Full rate during the works, half rate after practical completion. The notice you send always matches your dashboard. See how it works Approvals A certificate or an enquiry goes out on a link, and the answer is written into the document with the figure frozen into it. See how it works Completion and certificates Practical completion, sections and partial possession. Issuing it halves the retention and stops the damages clock. See how it works Extensions of time A relevant event named on every delay claim, and a warning when an event carrying time alone is claimed for money. See how it works Final account and reports Every adjustment from the contract sum to the final balance due, and the anticipated cost against the approved budget. See how it works Cash flow forecast Receipts against payments on the dates money actually moves, with the funding peak the job reaches before it turns. See how it works Risk register Each risk with a probability and a cost, so the allowance is the expected value and the contingency is calculated. See how it works Audit trail Who changed which figure and when, not editable and exportable to CSV. If a valuation is challenged, it already exists. See how it works Client and team access Send a guest link and the client sees their own position. Guests never count towards your plan or see your cost report. See how it works Programme and records Gantt against the contract period, drawings versioned, photographs, tasks and RFIs, all held against the same project. See how it works

See all 29 features

Free, and no account needed

Payment date calculator

Put in your contract form and the date of the application, and get the four dates back: payment due, payment notice, pay-less deadline and the final date for payment. Nothing is saved and nothing is asked of you.

Open the calculator

Three firms, three ways in, all of them real

No logos we were not given and no quotes nobody said. Three interviews written up in full, including the parts where QScope was not the answer.

Work it out on your own numbers

Every assumption below is yours to set, including how much time you think QScope would save you. We have not put a single figure of our own into this calculation.

Your own figure, a year

£0

Eight hours at forty-five pounds, halved, is the starting point on the sliders, not a claim. Change all three and the figure changes with them.

Put it against what a project costs

One price for the whole of it

On your own

£199/month

  • 2 users · 10 active projects
  • Unlimited client and subcontractor guests
  • Payment dates from your own contract terms, confirmed once
  • Certificates, valuations and reports laid out by a practising QS
  • Retention handled automatically: half rate at PC, nil after release
  • Variations, advance payments and the final account
  • Commercial risk register with a calculated allowance
  • Audit trail: who changed what and when, exportable
  • Your firm logo on every document
  • Add users beyond your plan: £40 a month or £360 a year each
Start free

Most popular

Small team

£449/month

  • 8 users · 40 active projects
  • Unlimited client and subcontractor guests
  • Payment dates from your own contract terms, confirmed once
  • Certificates, valuations and reports laid out by a practising QS
  • Retention handled automatically: half rate at PC, nil after release
  • Variations, advance payments and the final account
  • Commercial risk register with a calculated allowance
  • Audit trail: who changed what and when, exportable
  • Your firm logo on every document
  • Everyone with their own login and their own audit record
Start free

Whole business

£849/month

  • Unlimited users · unlimited projects
  • Unlimited client and subcontractor guests
  • Payment dates from your own contract terms, confirmed once
  • Certificates, valuations and reports laid out by a practising QS
  • Retention handled automatically: half rate at PC, nil after release
  • Variations, advance payments and the final account
  • Commercial risk register with a calculated allowance
  • Audit trail: who changed what and when, exportable
  • Your firm logo on every document
  • Guided onboarding, data setup and a named contact
Start free

Every screen above is on every plan. There is no tier that takes retention away, and no tier that charges you again for the certificate at the end of a job you already paid for. What changes between plans is how many projects you run at once.

See full pricing

FAQs

No. Documents carry your practice name and your logo. QScope does not appear on anything you send a client.

Yes. Set the contract form to FIDIC and the certificate becomes an Interim Payment Certificate valued from the Contractor’s Statement, with the 28 and 56 day sequence counted in calendar days on the 1999 Red Book defaults. The dates are published starting points to verify against your Particular Conditions and jurisdiction.

Yes. If your bill is in an awkward format, send it to support and we will tell you the quickest route rather than leaving you to fight it. Either way the sections and subtotals you priced are preserved.

No. The cost side is entered by hand and stays that way. The program has no access to your accounts, and pretending it did would be the worst possible choice in a report about margin.

QScope detects it and warns the second person rather than letting one silently overwrite the other. Losing an afternoon of valuation because a colleague had the job open is not an acceptable failure mode.

Yes, to CSV, per project. It opens in Excel with a byte order mark so names with accents are not mangled, which matters when the file goes into a bundle.

From the blog

The part nobody teaches you, written down

One hundred and seventy four pieces on the commercial side of a contract. No sign-up, and no piece that ends in a sales pitch.

All 174 pieces

Put one live project in and see what comes out

Not a sample and not a tour. Your own job, your own contract dates, and the certificate that comes out of the other end. Thirty days, no card, and nothing to cancel if you walk away.

Rather ask first? Write to help@qscope.co.uk and you will get a reply within one working day, Monday to Friday.