QScope

Reports

The reports you actually send

Not a report builder with forty options. Four documents a QS produces every month, each already laid out the way a client expects to receive it.

  • Your practice name and logo, never QScope branding
  • Client purchase order printed so their accounts team can match it
  • Totals closed with a double rule, the accounting convention

30 days free, no card.

Reports
What prints
Cost report, anticipated final costClient
Retention noticeClient
Payment scheduleClient
Variation registerClient
Risk registerInternal

Every document QScope prints is black and white, with negative amounts in brackets and figures set in tabular numerals so columns line up.

Printed to survive a bundle

Reports get photocopied, scanned and attached to adjudication papers.

Anything that relies on colour stops being readable at that point, and a report that cannot be read is a report that cannot be relied on. Every document QScope prints is black and white, with negative amounts in brackets and figures set in tabular numerals so columns line up.

Reports

Cost report: tell them early

A cost report exists so the client hears about an overrun while something can still be done about it.

  • Anticipated final cost against approved budget, variance stated as a figure
  • Committed but not yet certified shown separately from certified
  • Contingency carried from the risk register, so it can be defended
Reports
Cost report to client
Approved budget
£230,000
Anticipated
£224,800
Variance
+£5,200
Certified to date£84,115.00
Committed, not certified£18,400.00
Risk allowance carried£5,200.00
Anticipated final cost£224,800.00

Anticipated final cost sits against the approved budget from the first valuation onwards, with the contingency drawn from your risk register rather than guessed.

Reports

Retention notice and payment schedule

Two documents that exist to stop an argument before it starts.

  • Retention held, released at practical completion or Taking-Over on FIDIC, and the balance date
  • Every certificate with net due, received and outstanding
  • Variation register listing each change, its basis and its status
Reports
Payment schedule
CertificateDueReceived
PC-01, 15 May 2026£3,482£3,482
PC-02, 15 Jun 2026£428£428
PC-03, 15 Jul 2026£9,140Outstanding
Outstanding to date£9,140.00

Two documents that exist to stop an argument before it starts. The retention notice tells the client exactly what is held and when it comes back. The payment schedule shows every certificate, what was due and what was received.

See it running before you sign up

Cash flow

The cash forecast a funder actually asks for

A cost report tells the client where the final number is heading.

  • Peak funding and the month it occurs stated as figures
  • Receipts from certificates against payments to subcontractors
  • Cumulative position printed month by month
Cash flow
Forecast for the funder
Peak funding
£186,400
Occurs
Nov 26
Cycles left
5
Sep 26 · actual(£142,900)
Oct 26 · actual(£171,300)
Nov 26 · forecast(£186,400)
Dec 26 · forecast(£164,100)

The forecast is built from the certificates already issued and the valuation schedule ahead, so the peak funding requirement is a document you can hand over rather than a figure defended from memory.

Cost and value

The report you keep, behind the one you send

The cost report faces the client and never mentions margin.

  • Value earned against cost incurred to one cut-off date
  • Margin and margin percentage, period by period
  • Kept internal, hidden from client guest links
Cost and value
Period to 30 Nov 26
Value
£93,300
Cost
£86,100
Margin
7.7%
Certified value£84,115
Done, not certified£6,400
Variations at settlement value£2,785
Value to the cut-off£93,300

Both work from one cut-off date, so the anticipated final cost you show the client and the margin you keep to yourself are two views of the same period, not two different projects.

Dashboard

Every report is the live position, printed

The reports are not a separate set of numbers you keep in step by hand.

  • Figures recalculated as you value, across every project
  • Contract sum, certified, retention and due this period first
  • The closest statutory deadline shown underneath
Dashboard
Ref 001, 11 Essex Road
Contract sum
£220,250
Certified to date
£84,115
Retention held
£4,205
Due this period
£14,031
Payment positionDateStatus
Last date for payment notice20 AugIssued
Last date for a pay-less notice24 Aug4 days
Final date for payment29 AugDue

Contract sum, certified to date, retention held and due this period stay current as you value, so the cost report you send and the figure you quote on the phone are the same figure.

Who it is for

One record, four reports that must agree

You are applying

You report cost against money secured

You report cost against the sum you have actually secured, and the difference between the two is the conversation with your own board.

Applying for payment
the same measurement

You are certifying

You report on figures you certified

You report to the client on a job you certify, and the report has to reconcile with the certificates you signed.

Certifying payment

You are doing both

Your record is the only report there is

You are the report: what you have applied for, what has been certified and what is still to fund, pulled from your own record.

Doing both yourself

You are reporting

You turn the record into a drawdown

You turn the project record into a drawdown recommendation, and the figures have to reconcile before the lender releases a pound.

Recommending a drawdown

The client, the architect and the tenderer are not on this list. They are the people you let in on a link: they see the one document you sent them, answer it, and that answer is written into the record. No account, no licence, no charge, on every plan.

FAQs

The questions this page raises most often, answered without a sales pitch at the end.

The layout is fixed, and deliberately so. These are documents that go into client files and adjudication bundles, and a consistent format is worth more than a configurable one. What changes is your logo, your practice name and your client reference.

Because certificates and reports get photocopied and scanned. A figure that is only red stops being a warning once it is grey. Negative amounts appear in brackets instead, which is the accounting convention and survives any amount of copying.

Not unless you print it for them deliberately. It is hidden from guest links by default, because a client who can read your contingency will always want to negotiate it.

Yes. The audit trail exports to CSV, and project data can be exported at any time, including during a trial and for 60 days after a cancellation.

From the blog

The part nobody teaches you, written down

Three pieces from the same corner of a contract as this page, answered at length and without a sales pitch at the end.

All 174 pieces

Keep reading

The three parts this page leans on

The reports you actually send

Not a report builder with forty options. Four documents a QS produces every month, each already laid out the way a client expects to receive it.

30 days free, no card.

Rather ask first? Write to help@qscope.co.uk and you will get a reply within one working day, Monday to Friday.