Dayworks
Daywork sheets and percentage additions
The contract states three separate percentages because they cover three different things. Applying an average to the lot is quick, and it is the reason the sheet comes back.
QScope Team·4 min read
Enter the three additions once
- Open Dayworks.
- Enter the addition on labour, on materials and on plant from your contract particulars.
- Every sheet from then on uses them.
Add a sheet
- Add a sheet with its number, date and a description of what the work was.
- Enter the net labour, materials and plant separately.
- Link it to the instruction that authorised the work.
- QScope shows the sheet total with each addition applied to its own element.
Agreed is not the same as submitted
Only sheets marked as agreed are carried into the final account. Submitted and disputed sheets are totalled separately so you can see both without confusing them.
- When a sheet is agreed, change its status.
- Click Use in final account to carry the agreed total into the dayworks line.
When daywork applies at all
Only where the work cannot properly be valued by measurement at contract rates. Where a rate exists, the rate applies. Daywork is not a choice between two ways of valuing the same work, and presenting it as one is how a sheet gets rejected on principle.
Daywork on a FIDIC contract
The mechanics are the same, the clause is different. On a FIDIC contract a variation of a minor or incidental nature can be instructed on a daywork basis under Sub-Clause 13.6, priced against the Daywork Schedule in the Contract rather than three contract percentages.
- Set the project to the FIDIC contract form.
- Record the clause on the variation as 13.6.
- Enter the resources used against the Daywork Schedule rates.
- The certified total is carried into the monthly Statement, and the certificate and payment dates run in calendar days.