NEC3 and NEC4 ECC
NEC does not use JCT valuation dates, JCT certificates or JCT retention. It uses assessment dates, a Project Manager and Option X16. QScope follows the NEC mechanism instead of bending it into a JCT shape, because the differences are where the money and the deadlines move.
30 days free, no card.
Under Option Y(UK)2, the option that makes an NEC contract comply with the Construction Act, the payment becomes due seven days after the assessment date, and the final date for payment follows from there. QScope derives the notice, the pay less deadline and the final date from the assessment date automatically.
Under NEC the amount due is assessed at each assessment date, not at a JCT interim valuation date.
Every statutory deadline that follows is measured from it, so the assessment date is the pivot the rest of the timetable turns on. Under Option Y(UK)2, the option that makes an NEC contract comply with the Construction Act, the payment becomes due seven days after the assessment date, and the final date for payment follows from there. QScope derives the notice, the pay less deadline and the final date from the assessment date automatically.
NEC payment certificate
Under NEC the Project Manager certifies the payment.
Assessed by the Project Manager at the assessment date of 24 August 2026. Payment becomes due on 31 August 2026.
Retention (X16)
NEC has no retention unless secondary Option X16 was included.
Where X16 applies, QScope holds retention on the Price for Work Done to Date above the retention free amount, at the percentage your Contract Data states, and releases it on the NEC triggers rather than the JCT ones.
Client Valuations
The way QScope values the works does not change between forms.
That means a practice running both JCT and NEC jobs works one way, not two, and the certificate a client receives reads the same whichever form the job sits on.
Statutory payment dates
The value of NEC date handling is not one certificate, it is the whole job seen at once.
QScope puts the same statutory engine behind every NEC job on the account, so the dates you cannot afford to miss sit on the project list rather than in a spreadsheet somebody has to remember to open.
FIDIC payment dates
NEC is a UK form, but the same date engine also runs FIDIC, the dominant form on international work.
Calendar days from the Statement. Statutory dates and taxes are published starting points to verify locally.
Who it is for
You are applying
You start the clock with the applicationYou send the application and the clock starts. If the payment notice is late or missing, the sum you applied for becomes the sum that falls due.
Applying for paymentYou are certifying
Your notices are what the Act readsYou issue the notices, and the dates on them are the ones the Construction Act holds you to. A missed pay-less deadline is not an argument you can win.
Certifying paymentYou are doing both
You count the dates with nobody checkingYou send the application yourself and count the same four dates, with nobody to remind you which notice has to leave this week.
Doing both yourselfYou are reporting
You lend against dates that must holdYou confirm the drawdown timetable against the contractual payment dates, so the facility releases against dates that will actually hold.
Recommending a drawdownThe client, the architect and the tenderer are not on this list. They are the people you let in on a link: they see the one document you sent them, answer it, and that answer is written into the record. No account, no licence, no charge, on every plan.
The questions this page raises most often, answered without a sales pitch at the end.
NEC3 and NEC4 ECC, as a contract form for the payment cycle. Selecting it sets the assessment date as the basis for the timetable, names the certificate as a Project Manager payment certificate, and applies the NEC retention rules under Option X16.
It records each compensation event and its agreed value and carries that into the certificate, the same way it handles a variation. It does not replace the Project Manager's assessment of Defined Cost. The judgement stays with the Project Manager; QScope holds the record, the value and the certificate.
Under Y(UK)2 the payment becomes due seven days after the assessment date and the final date for payment fourteen days after that. QScope uses those periods by default and lets you change them if your Contract Data states different figures.
Only if secondary Option X16 is in the contract. QScope applies retention when you turn it on, at the percentage and retention free amount your Contract Data states, and releases it at Completion and the Defects Certificate rather than at practical completion.
Yes. FIDIC sits alongside JCT and NEC as a contract form, with a jurisdiction and currency setting per job. On FIDIC the Engineer issues the Interim Payment Certificate within 28 days of the Statement and the Employer pays within 56 days, counted in calendar days, with those periods editable for the Particular Conditions. A banner reminds you that statutory dates and taxes are published starting points to verify locally.
From the blog
Three pieces from the same corner of a contract as this page, answered at length and without a sales pitch at the end.
Court fees are published and start at 35 pounds; on bigger claims the issue fee is 5% of the sum. Adjudication has no fee table: each side carries its own costs. Which route eats less of the debt, with sources and read dates.
Read nowIn England and Wales, no. There is no construction lien, and materials built in belong to the property whether or not you have been paid. What you actually have instead, and the mistake that turns their debt into your problem.
Read nowIt can be, and the difference decides whether your figure becomes the sum they must pay. What a payment application needs, how long you have to send one, and why the wrong day can cost a whole cycle.
Read nowKeep reading
NEC does not use JCT valuation dates, JCT certificates or JCT retention. It uses assessment dates, a Project Manager and Option X16. QScope follows the NEC mechanism instead of bending it into a JCT shape, because the differences are where the money and the deadlines move.
30 days free, no card.
Rather ask first? Write to help@qscope.co.uk and you will get a reply within one working day, Monday to Friday.